A team member on a waterfall project tells the PM that the feature they were assigned is nearly complete but won't meet the quality standard. The PM should first:
- A.Work with the team member to understand the root cause
- B.Report the issue to the sponsor immediately
- C.Assign the task to a different team member
- D.Update the project schedule to reflect the delay
Show answer
Answer: A
First-response: investigate the issue. Understand scope and root cause before escalating or reassigning.