PMP Sample Questions
6 practice questions with complete answer explanations.
Sample Questions
A team member on a waterfall project tells the PM that the feature they were assigned is nearly complete but won't meet the quality standard. The PM should first:
Explanation
First-response: investigate the issue. Understand scope and root cause before escalating or reassigning.
A project's CPI is 0.85 and SPI is 1.05. What is true?
Explanation
CPI < 1 = over budget. SPI > 1 = ahead of schedule.
Two team members disagree about the technical approach for a module. The PM should:
Explanation
PMI prefers collaborative conflict resolution. The PM facilitates, doesn't decide for the team.
In a Scrum project, who is responsible for prioritizing the product backlog?
Explanation
The Product Owner owns the backlog and prioritizes based on business value.
During project execution, a stakeholder requests a significant scope change. The PM should first:
Explanation
Integrated change control: first assess impact, then route through the CCB.
A project is 80% complete but its original business justification is no longer valid. The PM should:
Explanation
If the business case is invalid, continuing wastes resources. The PM should escalate to the sponsor immediately.
Test-Taking Tips
- 1.Read the PMBOK Guide but don't memorize it — understand the intent and philosophy.
- 2.Think like PMI: proactive, process-driven, and collaborative. 'Communicate first' is usually right.
- 3.Know earned value formulas: EV, PV, AC, CPI, SPI, EAC, ETC, VAC.
- 4.Study Agile as much as Waterfall — about half the exam is agile/hybrid.
- 5.Use a Qbank (PrepCast or Andrew Ramdayal) for 500+ scenario questions.
- 6.Join a study group — explaining concepts to others reinforces understanding.
Ready to practice more?
Take an interactive quiz with these questions.